Delays have pushed the completion of a Nicosia highway ring road further down the line, with a new request for placing the deadline to August 5.
The transport and works ministry said on Monday that the initial extension was for June 16, 2024, three-and-a-half months later than the agreed March 1 deadline.
However, the contractor then requested a new deadline be set for June 25, due to the heatwave.
The contractor is now citing weather conditions and unforeseen extra work since January 1 as reasons for applying for the August 5 deadline.
The requests were examined by the ministry, however, and a new deadline has been set for July 15, after which €5,500 will be deducted from the payment for every day as a penalty until the completion of the project.
The contractor expects the circular road to be delivered in mid-August, except for a small section on Tseri avenue, which will be delivered at a later date and which will not affect highway traffic.
The first phase of the long-awaited project was expected to be completed by the end of March 2023. It includes a 7.5-kilometre motorway connecting the Nicosia to Limassol motorway in the Dali area with Tseri Avenue as well as 10 kilometres of extra roads, three flyovers, and a main roundabout.
The total estimated budget of the project, to be completed in five phases, is €350 million.
Upon completion, it will operate as a ring road and will connect three main roads, the Nicosia to Limassol motorway, the road from Nicosia to Kokkinotrimithia, and the road from Nicosia to Palaichori.
Click here to change your cookie preferences