Tenders for the four-lane Paphos-Polis Chrysochous road are expected to be launched in the first half of 2027 for both phases of the project, Transport Minister Evie Tsolaki announced on Monday, ...
The transport ministry assured on Friday that works on the Paphos-Polis Chrysochous highway would continue, based on legal procedures, realistic planning and financially substantiated positions.
Responding to criticism, the ministry ...
The board of tenders has rejected both bids for the Paphos to Polis Chrysochous Road, Transport Minister Evi Tsolaki confirmed on Friday.
Tsolaki informed the House finance committee the decision ...
The government said Thursday that by year’s end it plans to get the wheels turning on a significant segment of the planned highway linking Paphos to Polis Chrysochous.
Speaking ...
The tender award process for the first phase of the Paphos-Polis Chrysochous road remains pending, with an update on the project expected by the end of the month, Paphos chamber ...
The Christodoulides government has made a habit of pulling the plug on several public projects, regardless of the cost to the taxpayer. The most high profile termination was the Vassiliko ...
New bids submitted for the Paphos–Polis road project are coming in above initial cost estimates, the transport ministry and the public works department said on Friday, stressing that the ...
The Transport Ministry confirmed on Friday that two bids have been submitted for the design and construction of the Paphos–Polis Chrysochous highway section from Ayia Marinouda to Stroumbi,
Cyfield ...
The tender appeals authority has rejected all cancellation claims made by Aktor Group regarding the Paphos-Polis Chrysochous motorway project, the transport ministry announced on Thursday.
The decision, dated November 19, concerns ...
President Nikos Christodoulides on Friday night promised that the new road which will link Paphos and Polis Chrysochous will have four lanes when construction is complete.
“Our government … has decided ...
The design and build contract for the Paphos-Polis Chrysochous road, signed in 2021 under the previous administration, was ended because the contractor chose not to continue, the transport ministry said on ...
The new road which will link Paphos and Polis Chrysochous will cost a total of €90.2 million plus value added tax, the public works department said on Thursday.
It explained that ...
The government on Friday announced a new tender for the first phase of the road which will connect Paphos and Polis Chrysochous.
The first phase will connect the village of ...
Decisions regarding the Paphos-Polis Chrysochous motorway were the best possible solution, the Public Works Department (PWD) said on Thursday, adding that it would not engage in further discussions with former ...
The former auditor-general Odysseas Michaelides lashed out at the Christodoulides government accusing them of creating a financial and safety scandal over the controversial Paphos-Polis Chrysochous motorway.
“Instead of admitting its ...
The auditor general’s office has blamed the contractor for the termination of the Paphos-Polis road, saying that state authorities were not responsible despite having added to the delay, it ...
The poor road network of Paphos is preventing the city from living up to its full potential, Paphos Disy MP Charalambos Pazaros said on Tuesday.
Speaking in the House on ...
The government on Thursday signed a contract worth almost €3.5 million for improvement works on the Paphos-Polis road.
The contract was given to Araco Construction CY Limited. According to an announcement ...
The Paphos Court has dismissed a request by the contractor to disallow government officials access to the Paphos Polis road construction site, it was reported on Wednesday.
The court also ...
The House legal committee on Thursday called for improvements to the procedural framework surrounding public contracts, amid a wave of contracts being terminated by the government in the second half ...
The termination of the Paphos-Polis road construction contract has prompted strong reactions from both Disy and Akel, who blame each other and successive governments for issues affecting major public projects ...
Construction company Aktor (formerly Intrakat) is now seeking over €35 million in damages through the courts after the public works department terminated the contract with regarding the Paphos-Polis road project, according ...
The contractor responsible for building the new motorway linking Paphos and Polis Chrysochous has requested an additional €32,329,800 to complete phase one of the project by April 29, 2027 – three years later than ...
Within the next two weeks answers will be given for several stalled infrastructure projects, Minister of Transport Alexis Vafeades said on Wednesday.
Speaking on CyBC’s morning programme, Vafeades first ...